Judgments

Decision Information

Decision Content

T-814-83
W. & R. Plumbing & Heating Ltd. (Plaintiff)
v.
The Queen (Defendant)
Trial Division, Addy J.—Calgary, January 20, 21; Vancouver, February 3, 1986.
INDEXED AS: W. & R. PLUMBING & HEATING LTD. V. R.
Estoppel — Promissory estoppel — Construction contract between Crown and general contractor — Plaintiff supplying labour and equipment — General contractor not paying plain tiff — General policy of defendant to seek undertakings from contractors to pay suppliers and sub-contractors — Crown contracts usually providing for holdbacks to ensure discharge of undertakings — Policy not followed — Defendant paying general contractor in full without holdback — Whether defendant's previous practice amounting to promissory estop- pel — Only one of six basic conditions for promissory estoppel met — If action could be founded on promissory estoppel, it was not specifically pleaded — Action dismissed.
Crown — Contracts — Crown contracting for construction work — Plaintiff sub-contracting to supply labour and equip ment — Defendant paying general contractor in full without holdback contrary to usual practice — Failure by general contractor to pay plaintiff — Plaintiff arguing unjust enrich ment and promissory estoppel — No unjust enrichment of defendant — Conditions for successful plea of promissory estoppel not met — Action dismissed.
The defendant entered into a contract with Dimack Con struction Co. for construction work on a building. The plaintiff company, pursuant to a contract with Dimack, agreed to supply labour, materials and equipment for the plumbing and mechanical systems. Dimack failed to pay the plaintiff the sum of $19,100 due on completion of the work. No contract, either oral or written, exists between the parties in the present action. The plaintiff bases its claim on promissory estoppel and unjust enrichment.
Held, the action should be dismissed.
It is the general policy of the defendant, in the case of construction contracts, to insist that general contractors under take to pay all suppliers and sub-contractors. To ensure that such undertakings are carried out, the defendant withholds certain amounts until acceptable evidence is furnished that payment has been made. In the case at bar, that policy was not followed. The defendant paid Dimack in full, without any
holdbacks, after the contract had been substantially completed but before deficiencies were corrected.
The issue is whether the defendant's conduct in the present case, having regard to its previous practice, constitutes promis sory estoppel. Judicial opinions are divided as to whether promissory estoppel can be invoked to support a claim or used only as a defence. The weight of authorities appears to indicate that promissory estoppel can be invoked only as a means of opposing a claim. In any event, the circumstances herein did not satisfy all of the basic conditions necessary to a successful plea of promissory estoppel: (1) a promise by the person against whom the principle is invoked; (2) the promise must be clear and unequivocal; (3) the promisee must have changed his position as a result of the promise (most authorities maintain that the change must be to the detriment of the promisee; others, that it is sufficient if the promisee acts as a result of the promise); (4) a real legal relationship between the parties which is in existence, has recently been in existence or is in the course of being created; (5) the legal relationship must be affected by the promise to which the estoppel relates; (6) an intention of the promisor to affect the legal relationship with the promisee. The third condition had been met, there being evidence that the plaintiff would not have tendered on any contract with Dimack had it not been aware of the existence in the main contract of holdback provisions. None of the other requirements was fulfilled.
If an action can be founded on promissory estoppel, it would have to be specifically pleaded in the statement of claim. In the case at bar, not only was it not specifically pleaded but there was no pleading of any past, present or future legal relationship to which any promise could relate.
With respect to the question of unjust enrichment, the evi dence clearly established that the defendant had paid Dimack in full for the work performed. The only entity unjustly enriched was Dimack Construction, which had been paid for work it did not perform. There was therefore no question of unjust enrichment of the defendant.
CASES JUDICIALLY CONSIDERED CONSIDERED:
Pettkus v. Becker, [1980] 2 S.C.R. 834; Re Union Con struction Ltd. and Nova Scotia Power Corp. Ltd. et al. (1980), 111 D.L.R. (3d) 728 (N.S.C.A.); Burrows (John) Limited v. Subsurface Surveys Ltd. et al., [1968] S.C.R. 607.
REFERRED TO:
Crown Lumber Co. Ltd. v. Smythe et al., [1923] 3 D.L.R. 933 (Alta. CA.); Re Bodner Road Construction Ltd., [1963] 43 W.W.R. 641 (Man. Q.B.); Re Tudale
Explorations Ltd. and Bruce et al. (1978), 88 D.L.R. (3d) 584 (Ont. H.C.).
COUNSEL:
J. K. Megaffin for plaintiff. Ian Donahoe for defendant.
SOLICITORS:
Megaffin, Wong, Calgary, for plaintiff.
Deputy Attorney General of Canada for defendant.
The following are the reasons for judgment rendered in English by
ADDY J.: The facts in this case are quite simple. The defendant entered into a contract with Dimack Construction Company (hereinafter called "Dimack") for construction work on a building situated on lands of the defendant. The plaintiff entered into a contract with Dimack to supply labour, materials and equipment for the plumbing and mechanical systems as detailed in the first- mentioned contract. The plaintiff performed all of its work under the contract with Dimack but the latter has failed to pay it $19,100, being the balance legally due and payable to the plaintiff as of the date of completion.
Dimack, although not formally in bankruptcy, is actually in a state of insolvency and is apparently unable to pay. The plaintiff has in fact obtained judgment in the Supreme Court of Alberta against Dimack for $19,100, plus an amount adjudged to be payable for interest.
There exists no contract, either oral or written, between the parties to the present action. The plaintiff, however, in its statement of claim requests from the defendant payment of the afore said amount of $19,100 plus interest on the basis of the alleged unjust enrichment of the defendant. After the original pleadings were exchanged, a motion for dismissal that the claim did not reveal a cause of action was dismissed and a concurrent motion to amend the statement of claim was granted. A new motion to dismiss was made at the
opening of the trial on the grounds that the facts in the amended statement of claim still did not reveal a legal basis for unjust enrichment as there was no allegation that the defendant had really received anything for which it had not paid.
I might have been inclined to grant this motion but, in view of the fact that the parties were ready to proceed to trial forthwith, that the defendant did not intend to call any evidence, and that the plaintiff would be calling only two witnesses requiring only three or four hours of trial time, I decided to reserve my decision on the motion and hear the evidence on the off-chance that something in the testimony might form a basis for recovery, subject, perhaps, to possible further amendment of the pleadings if required.
In the case of Pettkus v. Becker, [1980] 2 S.C.R. 834, Dickson J., as he then was, stated at page 848:
In Rathwell I ventured to suggest there are three requirements to be satisfied before an unjust enrichment can be said to exist: an enrichment, a corresponding deprivation and absence of any juristic reason for the enrichment. This approach, it seems to me, is supported by general principles of equity that have been fashioned by the courts for centuries, though, admittedly, not in the context of matrimonial property controversies.
At trial it was clearly established that the defendant had in fact not only paid Dimack in full for the work performed but had, in all probability overpaid the latter as there remained many uncor- rected deficiencies under the main contract. It is quite obvious, therefore, that there can be no question of unjust enrichment of the defendant and the action from the standpoint seems to have been misconceived from the very beginning. The only person unjustly enriched was Dimack, having been paid for work which in fact it did not perform but which was performed by the plaintiff.
During the trial, however, although there was no allegation to that effect in the amended statement of claim, counsel for the plaintiff maintained that the claim was also based on the equitable doctrine of promissory estoppel.
It was established that it is in fact the general policy of the defendant in the case of construction contracts to insist that the general contractors undertake to pay all suppliers and sub-contractors and that the agents of the defendant generally attempt to ensure that such undertakings are in fact carried out by withholding certain amounts until some acceptable evidence is furnished, estab lishing that the sub-contractors and suppliers have in fact been paid. The evidence required by the defendant from its contractors is usually in the form of statutory declarations furnished from time to time by some agent or representative of the main contractor. The contract also contains gener al provisions to that effect. An example of the general form of contract is made part and parcel of the package of tender documents for the con tract and is made available on request to any person wishing to tender on a sub-contract with the general contractor. In the present case, a rep resentative of the plaintiff examined a copy of the proposed contract documents before tendering on its own contract with Dimack.
It has also been established that on several previous occasions the plaintiff tendered as a sub contractor with general contractors who were taking on government construction works. On each such occasion a representative of the plaintiff examined the tender package for the main contrac tor. The principal reasons for doing so were, of course, to verify the plans, specifications and other conditions pertaining to the portion of the work which it would be called upon to carry out for the general contractor, and to examine other require ments such as completion dates for the various phases and sub-trades, the quality of the work required to be executed, and the nature and extent of any guarantees required by the owner. There was, however, evidence which I accept to the effect that the plaintiff would not have tendered on the sub-contract with Dimack had it not been aware of the general policy of the defendant to attempt to protect the sub-contractors and suppliers as previ ously mentioned. On four previous occasions the plaintiff was in fact successful in obtaining work as a sub-contractor on government construction projects and, on one of those occasions, after experiencing difficulty in being paid by the general
contractor, it finally obtained its money because the defendant held back on the monies due the general contractor until the plaintiff's claim was satisfied.
In the present case, the defendant paid Dimack in full after the contract was substantially com pleted but before many of the deficiencies had been corrected. There was also evidence to the effect that the work on other parts of the main contract had not been satisfactorily executed. Pay ment in full in such circumstances was apparently quite contrary to the normal policy of the defend ant. The reason for doing so in this case appears to be because the fiscal year of the defendant was ending and there still remained in the hands of what was termed the "client department", namely, the Department of Agriculture in this particular case, an unexpended balance from the current year's appropriations. In other words, the Depart ment followed the usual wasteful practice employed by various government departments of expending as quickly as possible all monies allocat ed for any given fiscal year in order to ensure that as much money as possible will be made available for the following year.
It is also of interest to note that, in lieu of awarding one contract to the general contractor, the work, although relatively minor and quite simple, was divided into three phases and a sepa rate contract was awarded to Dimack for each of the three phases, thereby bringing the amount of each contract within the authorized spending powers of the Department concerned without it being obliged to seek approval for the expenditure from higher authority as would have been the case had only one contract been awarded to Dimack for the work. In addition, contrary to the usual proce dure of making progress payments with holdbacks following periodical inspections as the work pro gressed, all three contracts were paid in full, with out any holdbacks, at the same time immediately before the fiscal year ended. The comprehensive list of deficiencies was only prepared and made available two months later.
The Minister of Public Works, in seeking to explain to the plaintiff why the usual procedures were not followed, attributed the cause to an "administrative error" of the Department. A much stronger term would undoubtedly have been more appropriate. However, no matter how much one might be attempted to criticize the manner in which responsible departmental authorities, having regard to their duties as public servants, handled the entire situation, that issue is not before this Court: the issue is simply whether the conduct of the defendant in the present case, having regard to its previous practice and conduct, can constitute promissory estoppel, or some other legal basis, on which the plaintiff can found its claim.
A sub-contractor cannot rely as a basis for recovery against the owner on the fact that the prime contract contains provisions obliging the main contractor to pay its sub-contractors' accounts. (See: Crown Lumber Co. Ltd. v. Smythe et al., [1923] 3 D.L.R. 933 (Alta. C.A.); Re Bodner Road Construction Ltd., [1963] 43 W.W.R. 641 (Man. Q.B.).) This principle also applies even where the main contract has a provi sion permitting the owner to pay sub-contractors directly, although this is obviously not the case here.
In the case of Re Union Construction Ltd. and Nova Scotia Power Corp. Ltd. et al. (1980), 111 D.L.R. (3d) 728 (N.S.C.A.), the Trial Judge held that the provisions for holdback in the main con tract constituted an inducement to the sub-con tractors and therefore consideration which created a constructive trust in favour of the sub-contrac tors. On appeal this concept was completely reject ed. Cooper J.A., in delivering judgment orally on behalf of the Court, stated at page 747 of the above-mentioned report:
The central point in this appeal is whether the learned trial Judge, Mr. Justice Burchell, was in error in finding that Nova Scotia Power Corporation is holding the sum of $213,843.70 as a holdback under the terms of the contract between it and Lundrigans Limited for the construction of the corporation's generating station at Lingan as constructive trustee and that the beneficiaries of that trust are persons variously referred to as sub-contractors, job creditors or third party claimants.
We are unanimously of the opinion that, with respect, the learned trial Judge was in error in finding such a trust. This is not a situation in which the concept of constructive trust applies.
As to the question of promissory estoppel, it seems that courts, generally speaking, have refused to even consider the possibility of promissory estoppel being capable of supporting a claim and have only recognized it as a means of opposing one. It has very often been stated that promissory estoppel can only be used as a shield and not as a sword. Certain pronouncements of Lord Denning, however, threw some doubt on whether the doc trine of promissory estoppel should be applied in so strict a fashion. On that question Ritchie J., speak ing on behalf of the Supreme Court of Canada in the case of Burrows (John) Limited v. Subsurface Surveys Ltd. et al., [1968] S.C.R. 607, stated at pages 614-615:
Since the decision of the present Lord Denning in the case of Central London Property Trust Ltd. v. High Trees House Ltd. ([1947] K.B. 130), there has been a great deal of discussion, both academic and judicial, on the question of whether that decision extended the doctrine of estoppel beyond the limits which had been theretofore fixed, but in this Court in the case of Conwest Exploration Co. Ltd. et al. v. Letain ([1964] S.C.R. 20 at 28), Mr. Justice Judson, speaking for the majority of the Court, expressed the view that Lord Denning's statement had not done anything more than restate the principle expressed by Lord Cairns in Hughes v. Metropolitan Railway Co. ((1877), 2 App. Cas. 439) in the following terms:
It is the first principle upon which all courts of equity proceed, that if parties, who have entered into definite and distinct terms, involving certain legal results—certain penal ties or legal forfeiture—afterwards by their own act or with their own consent, enter upon a course of negotiation which has the effect of leading one of the parties to suppose that the strict rights arising under the contract will not be enforced, or will be kept in suspense, or held in abeyance, the person who otherwise might have enforced those rights will not be allowed to enforce them where it would be inequitable, having regard to the dealings which have thus taken place between the parties.
In the case of Combe v. Combe ([1951] 1 All E.R. 767), Lord Denning recognized the fact that some people had treated his decision in the High Trees case as having extended the principle stated by Lord Cairns and he was careful to restate the matter in the following terms:
The principle, as I understand it, is that where one party has, by his words or conduct, made to the other a promise or assurance which was intended to affect the legal relations between them and to be acted on accordingly, then, once the other party has taken him at his word and acted on it, the one who gave the promise or assurance cannot afterwards be allowed to revert to the previous legal relations as if no such promise or assurance had been made by him, but he must
accept their legal relations subject to the qualification which he himself has so introduced, even though it is not supported in point of law by any consideration, but only by his word.
The principle that promissory estoppel could be invoked by a plaintiff in support of a claim was also advanced by Grange J. in Re Tudale Explorations Ltd. and Bruce et al. (1978), 88 D.L.R. (3d) 584 (Ont. H.C.).
The weight of authority, however, still seems to indicate that promissory estoppel can only be invoked as a defence. Regardless of whether or not it can serve to found a claim, it is certain that, in order to rely on promissory estoppel, as distin guished from proprietary estoppel, certain basic conditions must all be fulfilled. Among them are the following:
1. There must be a promise by the person against whom the principle is invoked.
2. The promise must be clear and unequivocal.
3. The promisee must have changed his position as a result of the promise. Most authorities main tain that the change must be to the detriment of the promisee, although some authorities, including Lord Denning seem to say that it is sufficient if the promisee acts as a result of the promise.
4. There must be a real legal relationship be tween the parties which is in existence or possibly, according to dicta in some cases, was recently in existence or is in the course of being created.
5. The legal relationship must be affected by the promise to which the estoppel relates.
6. There must have been an intention of the promisor to affect the legal relationship with the promisee.
The plaintiff has fulfilled the third above men tioned condition, as there has been evidence which I accept, that it would not have tendered on any contract with Dimack and thus would not have been deprived of the $19,100 which it now claims, had it not been aware of the existence in the main contract of the defendant of the provisions regard-
ing holdbacks, etc., to which I have already referred. None of the other five requirements for promissory estoppel, however, have even remotely been met. The claim must therefore be dismissed.
Although the action must fail on the merits, it is of some importance to note that, if an action can in law be founded on promissory estoppel (and I refrain from stating any opinion on this issue) then it would seem axiomatic that for an action to be based on any such novel principle, it would have to be specifically pleaded in the statement of claim. At trial, counsel for the defendant quite rightly objected to the case being argued on the basis of promissory estoppel as the issue had never been raised in the pleadings. The plaintiff was invited by the Court to request an amendment to the statement of claim but declined to do so. Not only was promissory estoppel not specifically pleaded as the basis for the claim, but there was no pleading whatsoever as to any specific promise having been made by the defendant to the plaintiff at any time nor, of course, as to any particulars of any such promise. There was no pleading of any past, present or future legal relationship to which any promise might relate.
The action will be dismissed with costs.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.